Mitigation Banking - Marine and Fishery Resources Impacts
US Dept of Defence (Army Corps of Engineers)
Excerpts from
"Compensatory Mitigation for Losses of Aquatic Resources; Final Rule"
Federal Register / Vol. 73, No. 70 / Thursday, April 10, 2008 / Rules and Regulations
Interagency Review Team (IRT) = NMFS and USFWS
ABOUT MITIGATION BANKING
Mitigation bank means a site, or suite
of sites, where resources (e.g., wetlands,
streams, riparian areas) are restored,
established, enhanced, and/or preserved
for the purpose of providing
compensatory mitigation for impacts
authorized by DA permits.
In general, a mitigation bank sells compensatory
mitigation credits to permittees whose
obligation to provide compensatory
mitigation is then transferred to the
mitigation bank sponsor. The operation
and use of a mitigation bank are
governed by a mitigation banking
instrument.
Mitigation banking instrument means
the legal document for the
establishment, operation, and use of a
mitigation bank.
Release of credits means a
determination by the district engineer,
in consultation with the IRT, that
credits associated with an approved
mitigation plan are available for sale or
transfer, or in the case of an in-lieu fee
program, for fulfillment of advance
credit sales.
A proportion of projected
credits for a specific mitigation bank or
in-lieu fee project may be released upon
approval of the mitigation plan, with
additional credits released as milestones
specified in the credit release schedule
are achieved.
About Compensatory Mitigation
I. Background
As such, compensatory
mitigation is a critical tool in helping
the federal government to meet the
longstanding national goal of ‘‘no net
loss’’ of wetland acreage and function.
For impacts authorized under section
404, compensatory mitigation is not
considered until after all appropriate
and practicable steps have been taken to
first avoid and then minimize adverse
impacts to the aquatic ecosystem
pursuant to 40 CFR part 230 (i.e., the
CWA Section 404(b)(1) Guidelines).
Compensatory mitigation can be
carried out through four methods: the
restoration of a previously-existing
wetland or other aquatic site, the
enhancement of an existing aquatic
site’s functions, the establishment (i.e.,
creation) of a new aquatic site, or the
preservation of an existing aquatic site.
When compensating
for impacts to marine resources, the
location of the compensatory mitigation
site should be chosen to replace lost
functions and services within the same
marine ecological system (e.g., reef
complex, littoral drift cell).
MORE DEFINITIONS
Buffer means an upland, wetland,
and/or riparian area that protects and/or
enhances aquatic resource functions
associated with wetlands, rivers,
streams, lakes, marine, and estuarine
systems from disturbances associated
with adjacent land uses.
Compensatory mitigation means the
restoration (re-establishment or
rehabilitation), establishment (creation),
enhancement, and/or in certain
circumstances preservation of aquatic
resources for the purposes of offsetting
unavoidable adverse impacts which
remain after all appropriate and
practicable avoidance and minimization
has been achieved
Off-site means an area not located
on the same parcel of land as the
impact site, nor on a parcel of land
contiguous to the parcel containing the
impact site.
On-site means an area located on the
same parcel of land as the impact site,
or on a parcel of land contiguous to the
impact site.
Out-of-kind means a resource of a
different structural and functional type
from the impacted resource.
Preservation means the removal of a
threat to, or preventing the decline of,
aquatic resources by an action in or near
those aquatic resources. This term
includes activities commonly associated
with the protection and maintenance of
aquatic resources through the
implementation of appropriate legal and
physical mechanisms. Preservation does
not result in a gain of aquatic resource
area or functions.
Re-establishment means the
manipulation of the physical, chemical,
or biological characteristics of a site
with the goal of returning natural/
historic functions to a former aquatic
resource. Re-establishment results in
rebuilding a former aquatic resource and
results in a gain in aquatic resource area
and functions.
Reference aquatic resources are a set
of aquatic resources that represent the
full range of variability exhibited by a
regional class of aquatic resources as a
result of natural processes and
anthropogenic disturbances.
Rehabilitation means the
manipulation of the physical, chemical,
or biological characteristics of a site
with the goal of repairing natural/
historic functions to a degraded aquatic
resource. Rehabilitation results in a gain
in aquatic resource function, but does
not result in a gain in aquatic resource
area.
Release of credits means a
determination by the district engineer,
in consultation with the IRT, that
credits associated with an approved
mitigation plan are available for sale or
transfer, or in the case of an in-lieu fee
program, for fulfillment of advance
credit sales.
A proportion of projected
credits for a specific mitigation bank or
in-lieu fee project may be released upon
approval of the mitigation plan, with
additional credits released as milestones
specified in the credit release schedule
are achieved.
The appropriate watershed scale to use for the watershed approach will vary by geographic
region, as well as by the particular aquatic resources under consideration.
Since using a watershed approach is not appropriate in areas without watershed
boundaries, such as marine waters, we have also added a provision
(§ 332.3(c)(2)(v) [§ 230.93(c)(2)(v)]) to clarify that other types of spatial scales
may be more appropriate in those areas.
A few
commenters remarked that the proposed
rule does not adequately address
compensatory mitigation for marine
habitats or aquatic species.
We have revised the final rule to
better incorporate principles of
ecological restoration and landscape
ecology, for example, at § 332.3(d)
[§ 230.93(d)], which specifies detailed
factors for the district engineer to use in
determining ecological suitability for
mitigation project sites.
Section 404
directs the Corps to issue permits for
discharges of dredge and fill material,
not to promote ‘‘active management’’ of
wetlands. To the extent that active
management may provide an alternative
to permitted discharges, permit
applicants should consider such
approaches as part of the avoidance and
minimization mitigation sequencing.
Also, both permitted projects and
compensatory mitigation projects may
require on-going active management to
protect resources, and conditions for
such management may be incorporated
into DA permits where appropriate.
Finally, management of existing
wetlands may itself involve discharges
requiring DA permits, and in this case
permit conditions will address issues
related to the management and
protection of affected resources, in
accordance with applicable regulations,
including this rule. We disagree that the
rule does not adequately address marine
habitats and species. While the specific
projects needed to mitigate impacts to
marine resources may be different, the
procedural and analytical framework
established in the final rule applies
equally well to freshwater and marine
resources.
Several commenters said that the
proposed rule did not address concerns
raised in recent reports on
compensatory mitigation in the Corps
Regulatory Program that were issued by
the Government Accountability Office
(GAO). Some commenters said that the
proposed rule incorporates some of
GAO’s recommendations, but expressed
skepticism that the Corps has the
resources to implement those provisions
of this rule. These commenters asserted
that the Corps needs to make
compensatory mitigation compliance a
high priority to ensure effective
replacement of wetland acreage and
function lost as a result of permitted
activities.
Since
that provision was last promulgated in
1986, there have been policy changes
that have resulted in the Corps requiring
compensatory mitigation for more
activities, not just those that result in
significant resource losses. For example,
when the nationwide permit regulations
were revised in 1991, a provision was
added (33 CFR 330.1(e)(3)) which stated
that compensatory mitigation could be
required by a district engineer to ensure
that an NWP activity results in minimal
adverse environmental effects.
The final
rule issued today also specifically states
that it does not alter the regulations of
33 CFR 320.4(r), and that it supersedes
certain guidance documents on
compensatory mitigation. What is
generally understood to be
compensatory mitigation today (i.e., the
restoration, establishment,
enhancement, and/or preservation of
aquatic resources) is in the 404(b)(1)
Guidelines as an action to minimize
adverse effects on populations of plants
and animals (see 40 CFR 230.75(d)).
Compensatory mitigation may also be
required to satisfy other legal
requirements, as a result of the public
interest review process, or to
compensate for other resource losses. As
indicated in the preamble to this rule,
today’s rule does not affect the
determination as to when compensatory
mitigation is required, only the
requirements for conducting such
mitigation once the district engineer
determines that it is necessary.
As stated
in the preamble to the March 28, 2006,
proposed rule (71 FR 15524–15525), this
rule does not change the threshold for
determining when compensatory
mitigation is required; instead it focuses
on where and how compensatory
mitigation will be provided. The
threshold for determining when
compensatory mitigation is required for
DA permits is generally addressed
through 33 CFR 320.4(r) and specifically
for the nationwide permits at 33 CFR
330.1(e)(3).
projects.
Riparian areas. One commenter
suggested defining this term more
narrowly, to specify the type of
vegetation that characterizes riparian
areas. One commenter recommended
modifying this definition to limit it to
open waters, since wetlands are also
considered to be waterbodies.
We have modified the first sentence of
this definition to clarify that riparian
areas are lands adjacent to streams,
rivers, lakes, and marine-estuarine
shorelines. To simplify this definition,
we have also removed the second
sentence of the proposed definition.
In this paragraph, we
have added a provision to address
compensating for impacts to marine
resources. This provision states that
compensatory mitigation project sites
for marine resources should be located
in the same marine ecological system as
the impact site, citing reef complexes
and littoral drift cells as examples of
marine ecological systems. We have also
added provisions indicating that
compensation for impacts to aquatic
resources in coastal watersheds should
be located in a coastal watershed where
practicable,
To enhance the use of the watershed approach, we have added a sentence to
§ 332.3(c)(2)(iv) [§ 230.93(c)(2)(iv)] stating that the identification and
prioritization of resource needs should be as specific as possible.
(e) Dispute resolution process. (1)
Within 15 days of receipt of the district
engineer’s notification of intent to
approve an instrument or amendment,
the Regional Administrator of the U.S.
EPA, the Regional Director of the U.S.
Fish and Wildlife Service, the Regional
Director of the National Marine
Fisheries Service, and/or other senior
officials of agencies represented on the
IRT may notify the district engineer and
other IRT members by letter if they
object to the approval of the proposed
final instrument or amendment.
This
letter must include an explanation of
the basis for the objection and, where
feasible, offer recommendations for
resolving the objections. If the district
engineer does not receive any objections
within this time period, he may proceed
to final action on the instrument or
amendment.
(2) The district engineer must respond
to the objection within 30 days of
receipt of the letter. The district
engineer’s response may indicate an
intent to disapprove the instrument or
amendment as a result of the objection,
an intent to approve the instrument or
amendment despite the objection, or
may provide a modified instrument or
amendment that attempts to address the
objection. The district engineer’s
response must be provided to all IRT
members.
(3) Within 15 days of receipt of the
district engineer’s response, if the
Regional Administrator or Regional
Director is not satisfied with the
response he may forward the issue to
the Assistant Administrator for Water of
the U.S. EPA, the Assistant Secretary for
Fish and Wildlife and Parks of the U.S.
FWS, or the Undersecretary for Oceans
and Atmosphere of NOAA, as
appropriate, for review and must notify
the district engineer by letter via
electronic mail or facsimile machine
(with copies to all IRT members) that
the issue has been forwarded for
Headquarters review.
This step is
available only to the IRT members
representing these three federal
agencies, however other IRT members
who do not agree with the district
engineer’s final decision do not have to
sign the instrument or amendment or
recognize the mitigation bank or in-lieu
fee program for purposes of their own
programs and authorities.
Compensatory mitigation involves
actions taken to offset unavoidable
adverse impacts to wetlands, streams
and other aquatic resources authorized
by Clean Water Act section 404 permits
and other Department of the Army (DA)
permits.